Current Construction Projects

 

 

Measure O Bond Program

Martinez Unified School District Facilities & Construction Progress

 

Dashboard Status: Active Projects Weekly Progress Update
Report Date: October 5, 2026

TK Classroom Building

Delivery: Design-Build | Lead: Overaa / CG / MUSD
Master Plan Budget (MP) $3,000,000
Project Budget (PB) $4,525,816
Target Completion July 30, 2027

New 2 classroom TK building with staff restroom and conference room.

Latest Update (Week of 10/05)Exterior and interior wall framing layout.

Campus Wide Lighting Project

Delivery: TBD | Lead: Edward W. Scott / CG
Budget Included in TK Budget
Est. Construction Cost (ECC) $70,000

Exterior lighting improvement: library, old admin, MPR, and walkway canopy lighting

Latest Update (Week of 10/05) No new updates.
 
 

Bldg. J HVAC & Flooring Modernization

Delivery: Multi-Prime / OMNIA | Lead: BAM / CEC / ACF
HVAC Project Budget $2,002,840
Flooring Est. Cost (ECC) $543,869.22

New HVAC installation and Flooring for Building J

Latest Update (Week of 10/05)No new updates.

Campus Security Fencing (SPOE)

Delivery: Single Prime | Lead: Alta Fence / MUSD
Bldg. K & PAB Budget $93,416
Auto Shop & Fire Lane Budget $60,391

Fencing upgrades for security and safety.  

 

Latest Update (Week of 10/05) Contractor is tentatively scheduled to install the electronic hardware on October 12th.

Second Gymnasium

Delivery: Design-Build | Lead: OVERAA / SVA
Master Plan Budget (MP) $12,500,000
Project Budget (PB) $10,571,401
Target Completion July 30, 2027

Add new gymnasium with batrhooms and storage.

Latest Update (Week of 10/05)Prep for footing excavation and slab.

Upper Field, Track, and Tennis Courts

Delivery: Design-Build | Lead: Hellas / Huckabee
Master Plan Budget (MP) $5,000,000
Project Budget (PB) $6,525,704
Target Completion October 31, 2026

New tennis court concrete pad, surface, and fencing; new Track surface and installation of synthetic turf for interior field

Latest Update (Week of 10/05)No new updates.

AHS Building F Replacement

Delivery: Single Prime | Lead: TBD
Project Budget (PB) $28,8 million
Est. Construction Cost (ECC) $24.1 million

Replace Building F with a modern 17 classrom 2-story building; Replace HVAC in Gym, and Buildings A, B, C, D, & E.

Latest Update (Week of 10/05) No new updates.

 

 

Access Ramp & Admin Door Modernization

Delivery: Multi-Prime | Lead: CLS / RQI / Cumming Group
Ramp Budget (PB) $91,463
Door Budget (PB) $25,000

Security and access improvements to Administration building.

Latest Update (Week of 10/05)Contractor to fix punch list items for concrete work.