TK Playground Modernization
| Project Budget (PB) | $500,000 |
| Est. Construction Cost (ECC) | $495,016 |
| Playground Inspection | August 4, 2026 |
Synthetic turf installation completed; playground punch list is ongoing.
Martinez Unified School District Facilities & Construction Progress
| Project Budget (PB) | $500,000 |
| Est. Construction Cost (ECC) | $495,016 |
| Playground Inspection | August 4, 2026 |
Synthetic turf installation completed; playground punch list is ongoing.
| Master Plan Budget (MP) | $3,000,000 |
| Project Budget (PB) | $4,525,816 |
| Target Completion | July 30, 2027 |
DSA approval received; construction fencing installed.
| Budget | Included in TK Budget |
| Est. Construction Cost (ECC) | $70,000 |
Focus covers library, old admin, MPR, and walkway canopy lighting upgrades.
| HVAC Project Budget | $2,002,840 |
| Flooring Est. Cost (ECC) | $543,869.22 |
| LVT Target Finish | August 4, 2026 |
Patchwork, air balancing, power testing completed; floor installations underway.
| Bldg. K & PAB Budget | $93,416 |
| Auto Shop Budget | $60,391 |
Fencing upgrades progressing around key perimeter access points.
| Master Plan Budget (MP) | $12,500,000 |
| Project Budget (PB) | $10,571,401 |
| Target Completion | July 30, 2027 |
Phase 1 submittal in progress with DSA.
| Master Plan Budget (MP) | $5,000,000 |
| Project Budget (PB) | $6,525,704 |
| Target Completion | October 31, 2026 |
Phase 1 under 3–5 week DSA review process.
| Ramp Budget (PB) | $91,463 |
| Door Budget (PB) | $25,000 |
| Ramp Railings Install | August 4, 2026 |
Concrete pattern corrected; railings arriving along with new metal threshold.
| Project Budget (PB) | $30,000 |
| Status | Complete / Awaiting Base Trim |
Casework installation finished; electrical and carpet complete.
| Project Budget (PB) | $65,404 |
| Est. Construction Cost (ECC) | $48,447.08 |
| Status | COMPLETED |
New sign and marquee completely installed on building exterior.