Skip to main content

Martinez Unified School District

Dedicated to Excellence

Current Construction Projects

 

 

Measure O Bond Program

Martinez Unified School District Facilities & Construction Progress

 

Dashboard Status: Active Projects Weekly Progress Update
Report Date: August 3, 2026

TK Playground Modernization

Delivery: Multi-Prime | Contractor: Bosco / Miracle / Fieldturf
Project Budget (PB) $500,000
Est. Construction Cost (ECC) $495,016
Playground Inspection August 4, 2026

Synthetic turf installation completed; playground punch list is ongoing.

Latest Update (Week of 7/27 - 8/3) Synthetic turf installation finished. Initial inspection by the Playground Inspector scheduled for Tuesday, Aug 4.

TK Classroom Building

Delivery: Design-Build | Lead: Overaa / CG / MUSD
Master Plan Budget (MP) $3,000,000
Project Budget (PB) $4,525,816
Target Completion July 30, 2027

DSA approval received; construction fencing installed.

Latest Update (Week of 7/27 - 8/3) DSA approval received! Overaa installed perimeter fencing and will mobilize on-site (tentatively Aug 5) to begin site clearing, and grading.

Campus Wide Lighting Project

Delivery: TBD | Lead: Edward W. Scott / CG
Budget Included in TK Budget
Est. Construction Cost (ECC) $70,000

Focus covers library, old admin, MPR, and walkway canopy lighting upgrades.

Previous Update (7/22/26) Agreement finalizing with priority given to walkway canopy lighting.

Bldg. J HVAC & Flooring Modernization

Delivery: Multi-Prime / OMNIA | Lead: BAM / CEC / ACF
HVAC Project Budget $2,002,840
Flooring Est. Cost (ECC) $543,869.22
LVT Target Finish August 4, 2026

Patchwork, air balancing, power testing completed; floor installations underway.

Latest Update (Week of 7/27 - 8/3) Power load tests passed for new HVAC units. LVT tile installation in Room 203 completes Aug 4. First-floor classroom rubber base wall trim arriving late August.

Campus Security Fencing (SPOE)

Delivery: Single Prime | Lead: Alta Fence / MUSD
Bldg. K & PAB Budget $93,416
Auto Shop Budget $60,391

Fencing upgrades progressing around key perimeter access points.

Latest Update (Week of 7/27 - 8/3) Transom installation between Bldg K & PAB being finalized. Materials for the Auto Shop fence section arriving at contractor facility next week.

Second Gymnasium

Delivery: Design-Build | Lead: OVERAA / SVA
Master Plan Budget (MP) $12,500,000
Project Budget (PB) $10,571,401
Target Completion July 30, 2027

Phase 1 submittal in progress with DSA.

Previous Update (7/22/26) DSA Phase 1 submission target date scheduled for late July.

Upper Field, Track, and Tennis Courts

Delivery: Design-Build | Lead: Hellas / Huckabee
Master Plan Budget (MP) $5,000,000
Project Budget (PB) $6,525,704
Target Completion October 31, 2026

Phase 1 under 3–5 week DSA review process.

Previous Update (7/22/26) Phase 1 documents submitted to DSA for approval.

Access Ramp & Admin Door Modernization

Delivery: Multi-Prime | Lead: CLS / RQI / Cumming Group
Ramp Budget (PB) $91,463
Door Budget (PB) $25,000
Ramp Railings Install August 4, 2026

Concrete pattern corrected; railings arriving along with new metal threshold.

Latest Update (Week of 7/27 - 8/3) Concrete walkway nearing completion.  Railings/guardrails scheduled to install on Aug 4; Replacement door swap in Admin builidngscheduled for late August (existing door operational for Day 1). The metal threshold is arriving Aug 7.

Admin New Casework Replacement

Delivery: Multi-Prime | Lead: ACF / RLC / AMS
Project Budget (PB) $30,000
Status Complete / Awaiting Base Trim

Casework installation finished; electrical and carpet complete.

Previous Update (7/22/26) Casework walk completed; matching wall base installation pending shipment.

Marquee and School Name Sign

Delivery: Single Prime | Lead: TackEG / MUSD
Project Budget (PB) $65,404
Est. Construction Cost (ECC) $48,447.08
Status COMPLETED

New sign and marquee completely installed on building exterior.

Latest Update (Week of 7/27 - 8/3) Contractor successfully installed the new marquee sign. District to program digital features. Project complete!