Current Construction Projects

 

 

Measure O Bond Program

Martinez Unified School District Facilities & Construction Progress

 

Dashboard Status: Active Projects Weekly Progress Update
Report Date: August 26, 2026

TK Playground Modernization

Delivery: Multi-Prime | Contractor: Bosco / Miracle / Fieldturf
Project Budget (PB) $500,000
Est. Construction Cost (ECC) $495,016
Status COMPLETED

New playground equipment and synthetic turf for TK students

Latest Update (Week of 8/10) Project Complete

TK Classroom Building

Delivery: Design-Build | Lead: Overaa / CG / MUSD
Master Plan Budget (MP) $3,000,000
Project Budget (PB) $4,525,816
Target Completion July 30, 2027

New 2 classroom TK building with staff restroom and conference room.

Latest Update (Week of 8/24) Buidling pad grading complete; footing excavation later this week with a concrete pour date of 9/16

Campus Wide Lighting Project

Delivery: TBD | Lead: Edward W. Scott / CG
Budget Included in TK Budget
Est. Construction Cost (ECC) $70,000

Exterior lighting improvement: library, old admin, MPR, and walkway canopy lighting

Latest Update (Week of 8/24)Contactor investigatory report gave three phases for work – District to review and authorize appropriate phases

Bldg. J HVAC & Flooring Modernization

Delivery: Multi-Prime / OMNIA | Lead: BAM / CEC / ACF
HVAC Project Budget $2,002,840
Flooring Est. Cost (ECC) $543,869.22

New HVAC installation and Flooring for Building J

Latest Update (Week of 8/24) Nearing official closeout of project for phase 1 summer/fall 2026.  The building is fully accessible and operational for student instruction.

Campus Security Fencing (SPOE)

Delivery: Single Prime | Lead: Alta Fence / MUSD
Bldg. K & PAB Budget $93,416
Auto Shop & Fire Lane Budget $60,391

Fencing upgrades for security and safety.  

Latest Update (Week of 8/24) Autoshop & Fire Lane gate posts and gates will be installed by 9/1; Building K & PAB is waiting on additional electrical components, gates are operational

Second Gymnasium

Delivery: Design-Build | Lead: OVERAA / SVA
Master Plan Budget (MP) $12,500,000
Project Budget (PB) $10,571,401
Target Completion July 30, 2027

Add new gymnasium with batrhooms and storage.

Latest Update (Week of 8/24)No change: DSA Approval expected by the end of August

Upper Field, Track, and Tennis Courts

Delivery: Design-Build | Lead: Hellas / Huckabee
Master Plan Budget (MP) $5,000,000
Project Budget (PB) $6,525,704
Target Completion October 31, 2026

New tennis court concrete pad, surface, and fencing; new Track surface and installation of synthetic turf for interior field

Latest Update (Week of 8/24)District and contractor reviewing accessibility options for the project as required for DSA approval

AHS Marquee & School Sign

Delivery: Single Prime | Lead: TackEG / MUSD
Project Budget (PB) $75,000
Est. Construction Cost (ECC) $52,300.00
Final Cost TBD
Status COMPLETED

Replace broken signage with new digital signage

Latest Update (Week of 8/10) Project completed

 

AHS Building F Replacement

Delivery: Single Prime | Lead: TBD
Project Budget (PB) $28,8 million
Est. Construction Cost (ECC) $24.1 million

Replace Building F with a modern 17 classrom 2-story building; Replace HVAC in Gym, and Buildings A, B, C, D, & E.

Latest Update (Week of 8/24 Request for Proposals (RFP) completed; District to evaluate 4 proposals

Access Ramp & Admin Door Modernization

Delivery: Multi-Prime | Lead: CLS / RQI / Cumming Group
Ramp Budget (PB) $91,463
Door Budget (PB) $25,000

Security and access improvements to Administration building.

Latest Update (Week of 8/24)New door expected end of September; Contractor to fix punch list items for concrete work

Admin New Casework Replacement

Delivery: Multi-Prime | Lead: ACF / RLC / AMS
Project Budget (PB) $30,000
Status COMPLETED

New office casework – reception counter and carpet

Latest Update (Week of 8/10)Project complete

Marquee and School Name Sign

Delivery: Single Prime | Lead: TackEG / MUSD
Project Budget (PB) $65,404
Est. Construction Cost (ECC) $48,447.08
Actual Cost $34,454.04
Status COMPLETED

Install new digital signage board

Latest Update (Week of 8/24) Moving the location of the Marquee from a ground mounted installation to the current wall mounted installation saved the district approximately $13,000